The Federal Government has commissioned major transmission upgrades in Alausa and Lekki, Lagos, adding a combined 272MW of bulk power capacity to two of the state’s key economic corridors.
The projects, commissioned by the Minister of Power, Joseph Tegbe, are part of ongoing efforts to strengthen Nigeria’s national transmission network, eliminate infrastructure bottlenecks and improve the movement of available electricity to distribution companies and consumers.
At the Alausa transmission station, an ageing 30MVA transformer was replaced with a new 100MVA transformer. The intervention increased the station’s total capacity from 135MVA to 205MVA and raised the bulk power available to the Ikeja Electricity Distribution Company (IKEDC) by 80MW.
The Lekki project delivered an even larger expansion. The Transmission Company of Nigeria (TCN) installed two additional 60MVA, 132/33kV transformers alongside nine new 33kV feeders.
The upgrades increased the Lekki substation’s 132/33kV capacity from 120MVA to 240MVA, representing an additional 192MW of capacity.
Speaking during the commissioning ceremonies, Tegbe outlined the Federal Government’s approach to addressing infrastructure constraints in the power sector.
“Identify the bottleneck. Invest in it. Remove the constraint. Unlock the capacity.”